A construction project has the following activities and durations: A: 5 days B: 3 days C: 4 days D: 2 days E: 6 days Activity A precedes B and C, B precedes D, and C and D precede E. What is the critical path?
A - B - D - E
A - C - D - E
A - C - E
A - B - C - E